About Pipeline Segment 3
At the intersection of Gerber and Vineyard Roads, the pipeline will bifurcate, or split, in two branches. One branch (Segment 3) continues east on Gerber Road and through approximately four miles of open land to the Folsom South Canal. This portion of the pipeline is 72 inches in diameter and will transport up to 100 million gallons of water to EBMUD during dry years only. The water will discharge from the FRWA pipe into the Folsom South Canal and travel to the southern end of the canal, where it will be pumped through pipelines to EBMUD’s Mokelumne Aqueducts in San Joaquin County. From the aqueducts, the water will travel 90 miles for delivery to EBMUD customers.
|
Latest Construction News
Install 72-inch pipe between Excelsior Road and the Folsom South Canal FRWA will install construction fencing, string pipe, and install the 72-inch pipeline between Excelsior Road and the Folsom South Canal, just west of Grant Line Road. The work will take place between May and October. Install 72-inch pipeline on Gerber Road, between Vineyard and Excelsior Roads Traffic Controls: Gerber Road is closed to through traffic between Vineyard Road and Excelsior Road. Detours are established along Florin Road and Calvine Road.
General Information
Work Hours
7 am to 6 pm., Monday-Saturday
Construction Timeframe
October 2007 April 2008
Contact
(916) 420-8067
construction@frwa.com
|